A regional pharmaceutical manufacturer builds a full greenfield site in a PIC/S market. Production lines, QC laboratory, warehouse and utilities are built in parallel, and more than ten GxP systems come from different suppliers. An EPC contractor leads the build. This demonstration shows how validation across connected systems, data integrity and interface responsibilities can be planned and carried out together with every party.
Method demonstration | fictional scenarioMaterial quarantine and release
Material lot, quarantine and sampling; released after QA approval
Dispensing
Weights written to the EBR
Manufacturing
Process parameters and deviations
Packaging and serialization
Packaging record and serial numbers
QC testing
!Results and CDS raw data
Target practice
QC-approved results reach batch review through a validated interface and the Authorised Person decides release; if a transfer error or status mismatch occurs, the batch stays in quarantine
Current practice
The result-to-release interface is awaiting validation
Recommendation: Verify the transfer of results from LIMS to release, with the batch held in quarantine if a transfer error or status mismatch occurs
QA review, release by the Authorised Person, shipment
Batch review, release decision and shipping record
Data layer: these records must be complete, traceable and available for inspection
NR Scan findings
In this demonstration, an NR Scan sets out 8 management goals with recommended actions
Management goal
A new plant brings more than ten systems online. Planning computerized system validation alongside equipment qualification lets testing and documentation progress steadily, keeping the start-up schedule on firmer ground.
Applicable requirement and basis
PIC/S PE 009-18 Annex 11
Addressed by
Validation planningManagement goal
More than ten systems exchange data over dozens of links, such as lot status passing from ERP to the warehouse system. Putting each link into the traceability matrix, with its own test, also allows each interface to be explained promptly during inspection.
Applicable requirement and basis
PIC/S PE 009-18 Annex 11
Addressed by
Validation planningManagement goal
After LIMS approval, release status passes to both ERP and WMS, so the two systems show the same material status and shipping decisions rest on a clear basis. If a transfer error or status mismatch occurs, the batch remains in quarantine until the status is confirmed.
Applicable requirement and basis
PIC/S PE 009-18 Annex 11
Addressed by
Validation executionManagement goal
Laboratory systems are a common focus of data integrity inspections. With the audit trail enabled and reviewed at a defined frequency, every change to a result can be seen and explained.
Applicable requirement and basis
PIC/S PI 041-1 Good Practices for Data Management and Integrity in Regulated GMP/GDP Environments
Addressed by
Sustaining the validated stateManagement goal
Servers, virtualization, network and backup form the shared infrastructure for all applications. Assigning ownership and qualifying this infrastructure provides a documented basis for recovery whenever it is needed.
Applicable requirement and basis
PIC/S PE 009-18 Annex 15
Addressed by
Validation planningManagement goal
Managing equipment PLC/SCADA separately from the office network, and assessing every patch for its effect on the validated state under change control, helps keep systems in a validated state. The 2025 draft Annex 11 revision (consultation closed, not yet adopted) raises cybersecurity expectations; current expectations still rest on PIC/S PI 041 and Annex 11.
Applicable requirement and basis
PIC/S PI 041-1 Good Practices for Data Management and Integrity in Regulated GMP/GDP Environments
Addressed by
Validation planningManagement goal
Agreeing a shared template and minimum content with suppliers at procurement makes it quicker for QA to consolidate reports and retrieve records during inspection.
Applicable requirement and basis
PIC/S PE 009-18 Guide to GMP for Medicinal Products
Addressed by
Validation planningManagement goal
For convenience at shift change, line HMIs and MES sometimes use shared accounts. Individual accounts let every electronic record be attributed to one person.
Applicable requirement and basis
PIC/S PE 009-18 Annex 11
Addressed by
Validation execution| Recommended action | Management goal | Applicable requirement and basis | Addressed by |
|---|---|---|---|
| 01Plan computerized system validation alongside equipment qualification, in the same budget and scheduleResponsibilities | A new plant brings more than ten systems online. Planning computerized system validation alongside equipment qualification lets testing and documentation progress steadily, keeping the start-up schedule on firmer ground. | PIC/S PE 009-18 Annex 11 | Validation planning |
| 02Document every data interface between systems, with responsibility for design, testing and validationSystem interface | More than ten systems exchange data over dozens of links, such as lot status passing from ERP to the warehouse system. Putting each link into the traceability matrix, with its own test, also allows each interface to be explained promptly during inspection. | PIC/S PE 009-18 Annex 11 | Validation planning |
| 03Verify the transfer of results from LIMS to release, with the batch held in quarantine if a transfer error or status mismatch occursSystem interface | After LIMS approval, release status passes to both ERP and WMS, so the two systems show the same material status and shipping decisions rest on a clear basis. If a transfer error or status mismatch occurs, the batch remains in quarantine until the status is confirmed. | PIC/S PE 009-18 Annex 11 | Validation execution |
| 04Enable the CDS audit trail and review it at a defined frequencyData integrity | Laboratory systems are a common focus of data integrity inspections. With the audit trail enabled and reviewed at a defined frequency, every change to a result can be seen and explained. | PIC/S PI 041-1 Good Practices for Data Management and Integrity in Regulated GMP/GDP Environments | Sustaining the validated state |
| 05Assign ownership of servers, network and backups, and include them in the validation master planResponsibilities | Servers, virtualization, network and backup form the shared infrastructure for all applications. Assigning ownership and qualifying this infrastructure provides a documented basis for recovery whenever it is needed. | PIC/S PE 009-18 Annex 15 | Validation planning |
| 06Separate the production equipment network from the office network, and assess each patch for its effect on validationResponsibilities | Managing equipment PLC/SCADA separately from the office network, and assessing every patch for its effect on the validated state under change control, helps keep systems in a validated state. The 2025 draft Annex 11 revision (consultation closed, not yet adopted) raises cybersecurity expectations; current expectations still rest on PIC/S PI 041 and Annex 11. | PIC/S PI 041-1 Good Practices for Data Management and Integrity in Regulated GMP/GDP Environments | Validation planning |
| 07Agree common documentation templates with suppliers at procurementResponsibilities | Agreeing a shared template and minimum content with suppliers at procurement makes it quicker for QA to consolidate reports and retrieve records during inspection. | PIC/S PE 009-18 Guide to GMP for Medicinal Products | Validation planning |
| 08Replace shared line accounts with one account per person, so records and signatures trace to the individualData integrity | For convenience at shift change, line HMIs and MES sometimes use shared accounts. Individual accounts let every electronic record be attributed to one person. | PIC/S PE 009-18 Annex 11 | Validation execution |
Scope
- Full site: production lines, QC laboratory, raw material and finished goods warehouses, utilities (purified water, HVAC, compressed air), server room and OT network
- About 12–20 GxP computerized systems (ERP, MES/EBR, LIMS, eQMS, WMS, EMS, BMS, SCADA, serialization, etc.) delivered by multiple suppliers
- Applicable: the local GMP of the PIC/S Participating Authority, PIC/S Annex 1, 11 and 15; export markets may add EU GMP; whether 21 CFR Part 11 applies depends on predicate rules and record use
Stakeholders
- Board / Plant Director
- On-time start-up, a successful first GMP inspection and delivery within budget
- Quality Assurance
- A VMP, GxP system inventory and data integrity controls that can be supported with evidence at inspection
- Owner's Engineering / Project
- Interface coordination, FAT/SAT completed as planned, and schedule
- IT/OT
- Network architecture, access, backup and cybersecurity
- EPC contractor
- C&Q of equipment and utilities, on the contract schedule
- System suppliers
- Provide documentation for their own system and help confirm interface specifications
Request this diagnosis for your own systems
NR Scan has a fixed scope and fee. We review the systems and existing documents and deliver a gap analysis report, a risk assessment with risk priority numbers (RPN), and improvement priorities with a timeline. No obligation to continue.